Progress report · Draw #2
Visit of Apr 30
412 Oak St · compared against the Apr 16 visit
ElectricalComplete4 of 4 verified
ExteriorComplete6 of 6 verified
KitchenIn progress7 of 9 verified
Hall bathBehind2 of 5 verified
Verified this visit
Panel replaced and inspected. New 100A load center; sticker dated Apr 24. 📷 2
Kitchen cabinets set. Fronts on, hardware pending. 📷 3
Behind schedule
Hall bath subfloor still open at the drain. Same corner photographed Apr 16 — no change between visits. 📷 2
Before / after
31 items verified on site · 3 flagged